This first management report presents a snapshot of the work progress of netCommons at the end of Month 9 (September 2016). The first nine months of the project have run smoothly and the intended work has been carried out with regularity. Deliverables were completed on time and uploaded on the Grant Management system within a few days of the intended deadline (this one being the exception).
By Month 9 all WPs have started and in none of them emerged any impairment that can hamper the development in the foreseeable future. The next plenary meeting will be held in London at the endo of January 2017.